Industry News

Upgrading Your Hotel to a Modern Lock System: A Project Guide

April 10, 2025By Everest Smart Traders2 min read
Upgrading Your Hotel to a Modern Lock System: A Project Guide

Phase 1: Scoping and Planning

Begin with a full door audit. Walk every door in the hotel that requires access control: guest rooms, service corridors, housekeeping stores, laundry, kitchen, server room, gym, roof. Count and categorise each door. Note: door thickness, door type (timber/metal), existing mortise position, and whether there is power nearby.

For each door type, select the correct lock model. Timber doors in Nepal typically use a 60 mm backset mortise. Metal doors may require a different faceplate. Order 10% spare locks for breakage allowance.

Phase 2: Infrastructure Preparation

Before any locks arrive: confirm the front desk PC is dedicated to lock management software (no other critical software). Install the management software and test on a demo lock. Confirm the front desk encoder is working. Prepare a blank key card stock (budget 3 cards per room per year).

Phase 3: Installation Sequence

Install locks in this order: 1. Non-guest rooms first (service areas, back of house) — these allow staff to get familiar with the system without disturbing guests. 2. Unoccupied guest rooms — batch these during low occupancy. 3. Occupied rooms — only between 10:00–14:00 when guests are typically out; never leave a room unsecured overnight.

Phase 4: Software Configuration

Create the full room list in the software before issuing any cards. Set up all access levels. Test every lock in the software inventory. Configure check-in/check-out default times. Test the master card on every newly fitted lock before opening the room to guests.

Phase 5: Staff Training

Run a 2-hour training session for front desk staff covering: check-in card encoding, check-out card cancellation, duplicate card issuance for lost cards, emergency access procedures, and end-of-day audit download. Create a laminated quick-reference card for the front desk.

Phase 6: Guest Communication

Update the check-in process. Inform guests that RFID key cards should be kept away from mobile phones and wallets (which can demagnetise them). Brief staff on how to handle the most common guest complaint: "My card stopped working." (Answer: re-encode it at the front desk — takes 10 seconds.)

Phase 7: Post-Installation Audit

After 30 days of operation, download audit logs from all locks. Review for: any doors not appearing in logs (lock not connected to system), any master card being used outside emergency (investigate), battery warnings (replace immediately). Document findings and submit to management.

hotel locksproject managementhospitalityupgrade

Interested in our automation products?

Get a free consultation and quote from our team.